The Construction WIP Schedule: Percentage of Completion, Over and Under Billings, and What Your Surety Looks For

How a construction WIP schedule works: percentage of completion, over and under billings, profit fade, what sureties check, and the tax methods contractors use.

By 6 min readPublished

For a contractor, the income statement on its own says little about how the business is doing. A job that is 60% complete has costs on the books, partial billings sent to the owner, and profit that is only an estimate until the job closes. The work-in-progress (WIP) schedule is where those pieces are reconciled, job by job. It determines the revenue that hits the income statement, the over- and underbillings on the balance sheet, and, for many contractors, how much work a surety will bond.

This guide explains how a WIP schedule is built, how to read over- and underbillings and profit fade, what sureties and lenders look for, and how the tax methods for long-term contracts differ from the financial statement method. For a short version focused on bonding, see bonding capacity and the WIP schedule; for setting up job costing, see job costing for small contractors.

The columns of a WIP schedule

ColumnWhat it shows
Contract valueOriginal contract plus approved change orders
Estimated total costCosts to date plus estimated cost to complete
Estimated gross profitContract value minus estimated total cost
Costs to dateActual job costs incurred
Percentage completeCosts to date ÷ estimated total cost (cost-to-cost method)
Revenue earned to dateContract value × percentage complete
Billed to dateProgress billings sent to the owner
Overbilled / (underbilled)Billed to date minus revenue earned
Cost to completeEstimated total cost minus costs to date
BacklogContract value minus revenue earned

Most contractors use the cost-to-cost method to measure progress. Its reliability depends entirely on the estimated cost to complete, which should come from project managers job by job each month, not from a formula.

A worked example

A contractor has a $1,000,000 contract with an estimated total cost of $850,000. At month-end, $510,000 of costs have been incurred and $560,000 has been billed.

  • Percentage complete: $510,000 ÷ $850,000 = 60%.
  • Revenue earned: $1,000,000 × 60% = $600,000.
  • Gross profit earned: $600,000 − $510,000 = $90,000.
  • Billed $560,000 vs. earned $600,000: underbilled $40,000, recorded as an asset.

If the estimate to complete rises so that total cost is now $900,000, the job is 56.7% complete, earned revenue falls to about $566,700, and estimated gross profit drops from $150,000 to $100,000. That one-third drop in expected profit is profit fade, and the WIP schedule makes it visible while the job is still running.

Loss jobs. When a contract is expected to lose money, the entire expected loss is recognized immediately, not spread over the remaining work.

Reading over- and underbillings

Overbillings (billings in excess of costs and estimated earnings) are a liability: cash collected for work not yet performed. Moderate overbillings are healthy; they mean the job is funding itself. But overbilled cash is not profit, and spending it can leave a contractor short when the work catches up.

Underbillings (costs and estimated earnings in excess of billings) are an asset, but a soft one. They can mean:

  • Billing is lagging behind the work, often from slow pay applications or unapproved change orders.
  • Costs are running over estimate, so the percentage complete is inflated relative to real progress.
  • Estimates to complete are too optimistic.

Sureties often discount or exclude underbillings when calculating working capital, and large or growing underbillings prompt questions.

What sureties and lenders look for

Surety underwriting is built on the "three Cs": capital, capacity, and character. On the financial side:

  • Working capital and equity. Single-job and aggregate bonding limits are often set as multiples of adjusted working capital or equity. Receivables over 90 days, underbillings, and related-party balances are commonly excluded or discounted.
  • Quality of statements. As programs grow, sureties typically require financial statements reviewed and then audited by an outside CPA firm, on the percentage-of-completion method, with a WIP schedule.
  • WIP schedules quarterly. Many sureties want interim WIP schedules each quarter, not just at year-end.
  • Profit fade and gain. Consistent fade across jobs suggests weak estimating; consistent gain can suggest conservative estimates, or profit being held back.
  • Backlog. Gross profit in backlog relative to overhead shows whether the business can cover its costs.
  • Closed-job history. A schedule of completed jobs comparing bid margin to actual margin.

Getting the books ready for bonding usually means monthly job costing, monthly WIP schedules, accrual-basis statements, timely CPA review or audit, and a close process that ends within a few weeks of month-end (see how a monthly close works).

Financial statements vs. tax methods

For financial statements, revenue on construction contracts is recognized over time under ASC 606, generally measured with the cost-to-cost input method, which produces the WIP schedule above.

For taxes, Section 460 governs long-term contracts:

  • Large contractors must generally use the percentage-of-completion method for long-term contracts, with a look-back interest calculation on Form 8697 when the contract finishes, to correct for estimates that turned out wrong.
  • Small contractors, with average annual gross receipts of $32 million or less for 2026 ($33 million for 2027), can use the completed-contract method or another exempt method for contracts expected to be completed within two years. Under the completed-contract method, income is recognized when the job is finished, which can defer tax.
  • Home construction contracts are exempt from percentage of completion regardless of size.
  • Cash method. Small contractors under the same gross receipts test can generally use the cash method of accounting for tax, even when their financial statements are on the accrual or percentage-of-completion basis.

A contractor can therefore produce accrual, percentage-of-completion statements for its surety while filing taxes on the cash or completed-contract method. Switching tax methods requires Form 3115. See changing from cash to accrual.

Common WIP mistakes

  • Plugging the estimate to complete with budget minus costs to date, instead of a real reforecast.
  • Leaving change orders out until they are signed, or including unapproved ones as revenue.
  • Misclassifying costs between jobs, or leaving overhead and equipment costs out of job costs.
  • Ignoring retainage in billings and receivables reconciliation.
  • Updating the WIP schedule only at year-end, which hides fade until it is too late to act.

The short version

The WIP schedule converts job costs and billings into earned revenue using the percentage of completion, producing overbillings (a liability) and underbillings (an asset). It reveals profit fade while jobs are open and is the core document sureties use to set bonding capacity, along with working capital, equity, and reviewed or audited statements. For taxes, small contractors under $32 million of gross receipts for 2026 can use the cash or completed-contract method, which can differ from the financial statements.

Rubric Financial builds monthly job costing and WIP schedules for contractors, prepares surety-ready financial statements, and chooses tax methods that fit the business. See our construction industry page for more.

Sources

Figures are federal and current as of the date above. Tax law and inflation-adjusted amounts change; confirm current figures before acting.

Educational content, not tax, legal, investment, or accounting advice. Confirm the specifics with a CPA before acting. See our Terms.

Frequently asked questions

What is a WIP schedule in construction?

A work-in-progress schedule lists every open contract with its contract value, estimated total cost, costs incurred to date, percentage complete, revenue earned to date, amounts billed, and the resulting overbilling or underbilling. It is the bridge between job costing and the financial statements, and the report sureties and lenders rely on most.

What are overbillings and underbillings?

Under the percentage-of-completion method, revenue is earned in proportion to costs incurred. If you have billed more than you have earned, the difference is an overbilling, a liability on the balance sheet. If you have earned more than you have billed, it is an underbilling, an asset. Persistent large underbillings often signal cost overruns or billing problems, and sureties scrutinize them.

What do sureties look at for bonding capacity?

Sureties focus on working capital, equity, profitability, the WIP schedule, and the quality of financial statements. Single-job and aggregate bonding limits are often expressed as multiples of working capital or equity. They look for consistent job profitability, limited profit fade, reasonable underbillings, and timely reviewed or audited statements from an outside CPA, usually with a WIP schedule attached.

What is profit fade?

Profit fade is the decline in a job's estimated gross profit between the time it is bid or started and the time it is completed. A job bid at a 15% margin that finishes at 8% faded by seven points. Sureties and lenders track fade across jobs because it shows whether a contractor's estimates and project management are reliable.

Do contractors have to use percentage of completion for taxes?

Long-term contracts generally must use the percentage-of-completion method for tax purposes, but small contractors, with average annual gross receipts of $32 million or less for 2026 ($33 million for 2027), can use the completed-contract or another exempt method for contracts expected to be finished within two years. Home construction contracts are also exempt. The tax method can differ from the method used for financial statements.

About the author

Nirmala Murugesan, CA, CPA, Partner, Accounting

Partner leading Rubric Financial's accounting practice. CA and CPA with 20+ years across U.S. GAAP, IFRS, and cross-border entity accounting in India and the U.S.